Phase: Execute
This is the third phase of the project life cycle where all the plans are executed, monitored and controlled. Project Schedule in the diagram below impacts Financial Plan and at the same time is affected by it. Managing these two tasks in turn impact the other tasks in the yellow framed box below and are also affected by these tasks which are managed simultaneously.
DescriptionWork Breakdown StructureTeam AllocationWork Product Usage
Purpose
  • Drive tasks toward completion using optimal resources.
  • Delivering against the Project Success Plan Sections 1 and 2 plus approved Change Requests.
Relationships
Parent Activities
Key Considerations

Inputs

  • Approved Project Success Plan (Section 2)
  • Updated Financial Management Plan
  • Project Team fully engaged in the project
  • Approved Design


Outputs

  • Attain project objectives as defined in the PSP on time and within budget